Technology for the Olympic Park

This event explored each stage of SI assurance: scope verification; design assurance; delivery assurance; test and commissioning; utility risk assessments; systems proving; and systems recovery planning.

Systems Integration (SI) was responsible for developing and implementing a programme-wide strategy for delivery of systems capable of supporting LOCOG’s overlay and minimising redundancy in Legacy.  

Superfast broadband was a new requirement introduced late in the construction of the Athletes’ Village. Installation of the new technology required redesign and education of the contractors on the new technology.  The event described the value of appointing a dedicated telecoms manager to ensure successful installation

 

Gordon Shipley and Paul Hyde

Programme Wide Approach to Systems Delivery

Gordon Shipley, Head of Systems and Technology, ODA, and Paul Hyde, Systems Team manager, ODA

2012-01-18 | Communications Channel

>> go to webcast >> recommend to friend



Simon Fisher

The SuperFast Olympics

Simon Fisher, Principal Consultant Strategic - Network Design, BT Openreach

2012-01-18 | Communications Channel

>> go to webcast >> recommend to friend