Policy Submissions

S871a - Smart metering prospectus - part 1

Description

Smart metering implementation programme prospectus: IET comments to the Office of Gas and Electricity Markets (Ofgem).


Abstract

The roll-out of smart meters should not be accelerated unless it is demonstrable that a methodology can be developed that gives assurance of systems level functionality and scalability. A plan to install smart meters on a saturation basis in defined geographic zones, sufficient to provide an installed base for functionality proving purposes, should be considered. The DataCommsCo (DCC) capabilities at the heart of this smart meter/smart grid initiative should be in place early to avoid unnecessary upgrades to meter and wide area network (WAN) software. A technically competent “design authority” is required to take overall technical responsibility for the entire system.

Submission Details Submitted on 28 September 2010 to Office of Gas and Electricity Markets (Ofgem)


View more details of this submission



Keywords and Search Terms Electricity supply industry, Energy industry, Gas industry, Smart grid, Smart meters, Metering, Meters, Energy consumption