good morning guys and girls.
looking for a little bit of help if anyone feeling generous? im currently completing my 2396 design project and NEARLY completed it, however i have to create an electrical O&M Manual for my installation. now this is completly new to me as im an installation sparky by trade and never had to do anything like this. any help or infomation or even a sample of one would be appreciated. many thanks barry |
|
|
|
|
|
|
|
|
You should include an introduction, description and purpose of the installation, emergency procedures, manufacturers information including warranties and guarantees, maintenance requirements including recommended list of spares, record drawings, certification/commissioning results, residual H&S and environmental information and de-commissioning procedures.
Regards |
|
|
|
|
|
|
|
|
You don't need to complete the O&M manual, you just need to identify what "headings" it should contain and a brief description of what you would include under each heading.
Use this at your risk, but the sort of headings you are looking for are: The purpose of the installation and index of designers, installers etc (all interested parties) The technical specification of the installation and safety related information The operation of the installation and safety aspects Manufactureres information and recommendations on use of equipment Modifications to the systems Disposal of the systems As Installed drawings regards OMS ------------------------- Failure is always an option |
|
|
|
|
|
|
|
|
Barry this 20 point model is issued as a guide to the M&E contractors on my site in the production of the O&M manuals
Section 1 About the project Section 2 Change control Section 3 Emergency Escalation Procedure Section 4 Emergency Information Section 5 Emergency Equipment Locations Section 6 System Purpose and Scope Section 7 Contractual and Legal Information Section 8 Descriptions Section 9 Equipment Schedules and asset register Section 10Manufactures Operating Instructions and Procedures Section 11Manufactures Operating Manuals and Literature Section 12Maintenance Procedures Section 13Spare Parts and Consumables Section 14Disposal Instructions Section 15Testing and Commissioning Section 16Modifications Section 17Drawings Section 18Manufacturers and suppliers Literature Section 19Product Guarantees and Warranties Section 20Cross Referencing Index Hope this helps good luck with your project In a previous life as a contractor prior to the commencement of a new project it was always together with the risk assessment and method statement plus test sheets, the O&M manuals were started. The O&Ms put on the shelf and added to as the job progressed The O&Ms started at the beginning of the job not scurrying round at the end trying to complete MrP |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
thanks guys some useful information there for me to take on board.
looking forward to completing it and handing it in... nearly forgotten what my family look like. i think C&G have a different clock to me!! regards Barry |
|
|
|
|
|