IET logo
 
IET
Decrease font size
Increase font size
Topic Title: Standby generators
Topic Summary:
Created On: 15 March 2006 08:06 PM
Status: Read Only
Linear : Threading : Single : Branch
 Standby generators   - 00458807370 - 15 March 2006 08:06 PM  
 Standby generators   - mapj1 - 22 March 2006 11:11 PM  
 Standby generators   - weirdbeard - 28 August 2016 03:05 PM  
 Standby generators   - mapj1 - 28 August 2016 08:02 PM  
Search Topic Search Topic
Topic Tools Topic Tools
View similar topics View similar topics
View topic in raw text format. Print this topic.
 15 March 2006 08:06 PM
User is offline View Users Profile Print this message



00458807370

Posts: 8
Joined: 13 May 2003

C certificate regulations question,
I have come accross this question on an old C cert paper, can any body help with the answer.

A generator set is to be used as a temporary standby supply for a work shop whilst essential work is conducted on the sub station transformer.
1, describe the requirements of BS7671 with regard to,

the means of earthing the standby gen in relation to the public supply

the precautions to be taken regarding isolation of the public supply

a suitable means for automatic disconnection of the standby supply.

I have worked on my answers, but would appreciate anybody elses opinion on this.
cheers sn