It's over a year since we closed Savoy Place, and the project is now firmly into the construction phase. 

As of August 2014, the project continues well. Over the summer, major structural works have been completed to allow the build of the new lecture theatre at second floor level.

The building is now protected behind scaffolding and a waterproof covering, allowing the construction team to commence repairs to the brickwork and stonework on the facades. The existing windows are being replaced throughout, and the installation of new windows has commenced on the east facade. Internally, the new passenger lift shafts are under construction, and the majority of demolition work is coming to an end.

During the autumn the project will move into its second phase. This sees the first fix of the mechanical and electrical systems and the modernisation of the internal rooms to provide the new design layouts.

Watch our latest video update for more information.

Further detail on the project and our temporary London home at One Birdcage Walk is available on these General FAQs and Co-location FAQs pages (access for IET members only).

 

IET Connect

The IET Benevolent Fund, IET Connect, has re-located from Savoy Place to a new central London office: